Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 8 July 2024 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 8 – Friday 12 July
Block A:
External sheet boarding in progress
Scaffolding - 1st floor to 2nd floor
Waterproofing installation ready to splash course
Blockwork to Internal wall
Block B:
Building the structure to hold the concrete for 2nd floor
Concrete pour to columns
Preparing base for scaffolding
Service trenches at sections for water mains installation, including meter installation from Thames Water. Road closure for Thames Water has been re-scheduled to December when it will be quieter.
Block C:
Building the structure to hold the concrete for the 3rd floor
Scaffolding - ground floor to 1st floor
Building retaining wall
Waterproofing Installation
Otto Close:
Groundworks to foundations and drainage works ongoing
Sewage connection works on Otto Close - *See note below
Saturday 12 July (08.00 - 13.00)
Continuation of works listed above
Noisy works
Plant movement (excavators and dumpers)
Deliveries
Muck removal lorries in and out of main gate
Concrete lorries in and out of the delivery gate
Note
From Monday 8 July 2024 there will be a phased closure to parts of Otto Close to carry out works to the manholes to connect the new sewer to the existing sewer. Access for vehicles and pedestrians will be retained throughout, but parts of the road will be single file traffic around the fenced-off areas where work will be taking place. At the end of each day a road plate will be put over the manhole and the barriers will be removed to allow traffic to use the whole road safely.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact Lovell on:
Andrew Neary 07881 023 254
David Olatunji 07340 379305