Construction Timeline

The timeline below gives details of the activities that are due to take place in the coming months, as well as an overview of the project on a quarterly basis until completion. Completion and handover is currently estimated to be late 2025.

This is a working timeline that is subject to change. Updates will also be provided via the weekly works updates and resident newsletters.

  • Mais House

    Completion of substructure

    Frame

    Otto Close

    Drainage works by 23 Lammas Green

  • Mais House

    Frame

    Scaffold

    Roofing

    Envelope works

    Otto Close

    Drainage works

    Reduce level dig

    Pile mat and piling

  • Mais House

    Frame

    Scaffold

    Roofing

    Envelope works

    Otto Close

    Substructure and drainage

    Superstructure

    Scaffold

  • Mais House

    Roofing

    Envelope works

    Internals

    Otto Close

    Superstructure

    Roofing

    Envelope

    Internals

  • Mais House

    Roofing works

    Envelope works

    Internals

    Otto Close

    Internals

    Externals

  • Mais House

    Roofing

    Envelope Works

    Internals

    Externals

    Otto Close

    Internals & Externals

    Landscaping

  • Mais House

    Internals & Externals

    Balconies

    Landscaping

    Otto Close

    Externals

    Landscaping

  • Mais House & Otto Close

    Landscaping & Handover