Construction Timeline
The timeline below gives details of the activities that are due to take place in the coming months, as well as an overview of the project on a quarterly basis until completion. Completion and handover is currently estimated to be late 2025.
This is a working timeline that is subject to change. Updates will also be provided via the weekly works updates and resident newsletters.
-
Mais House
Completion of substructure
Frame
Otto Close
Drainage works by 23 Lammas Green
-
Mais House
Frame
Scaffold
Roofing
Envelope works
Otto Close
Drainage works
Reduce level dig
Pile mat and piling
-
Mais House
Frame
Scaffold
Roofing
Envelope works
Otto Close
Substructure and drainage
Superstructure
Scaffold
-
Mais House
Roofing
Envelope works
Internals
Otto Close
Superstructure
Roofing
Envelope
Internals
-
Mais House
Roofing works
Envelope works
Internals
Otto Close
Internals
Externals
-
Mais House
Roofing
Envelope Works
Internals
Externals
Otto Close
Internals & Externals
Landscaping
-
Mais House
Internals & Externals
Balconies
Landscaping
Otto Close
Externals
Landscaping
-
Mais House & Otto Close
Landscaping & Handover