Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Monday 1 July 2024 in connection with the Sydenham Hill Estate Redevelopment Project.
Monday 1 – Friday 5 July
Block A:
Scaffolding - ground floor to first floor ongoing
Waterproofing installation
Block B:
Building the structure to hold the concrete for 1st floor
Concrete pour to columns
Preparing base for scaffolding
Service trenches at sections for water mains installation, including meter installation from Thames Water
Block C:
Building the structure to hold the concrete for the 3rd floor
Building retaining wall
Waterproofing Installation
Otto Close:
Groundworks to foundations and drainage works ongoing
Saturday 6 July (08.00 - 13.00)
Continuation of works listed above
Noisy works
Plant movement (excavators and dumpers)
Deliveries
Muck removal lorries in and out of main gate
Concrete lorries in and out of the delivery gate
If you have any queries, please contact us on info@sydenhamhillproject.com
Best wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact Lovell on:
Andrew Neary 07881 023 254
David Olatunji 07340 379305
Peter Trainer 077779 992854