Sydenham Hill Estate Weekly Works - w/c 1 July 2024

Dear Neighbour,


Please find below the activities that are scheduled to take place from the week commencing Monday 1 July 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 1 – Friday 5 July

Block A:

  • Scaffolding - ground floor to first floor ongoing

  • Waterproofing installation

Block B:

  • Building the structure to hold the concrete for 1st floor

  • Concrete pour to columns

  • Preparing base for scaffolding

  • Service trenches at sections for water mains installation, including meter installation from Thames Water

Block C:

  • Building the structure to hold the concrete for the 3rd floor

  • Building retaining wall

  • Waterproofing Installation

Otto Close:

  • Groundworks to foundations and drainage works ongoing

Saturday 6 July (08.00 - 13.00)

  • Continuation of works listed above

Noisy works

  • Plant movement (excavators and dumpers)

Deliveries

  • Muck removal lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best wishes,

The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

For site emergencies, please contact Lovell on:

  • Andrew Neary 07881 023 254

  • David Olatunji 07340 379305

  • Peter Trainer 077779 992854