Monday 4 - Friday 8 November

Block A

  • Brickwork to 2nd – 3rd floors

  • Wall insulation – ground floor

  • Mechanical & electrical inspection - 1st floor

  • Internal walls – 3rd floor

  • Testing of mechanical pipework

  • Roof waterproofing works to gutter

  • Pitched roof tiling

Block B

  • Scaffolding installation to perimeter – 4th & 5th floor

  • Perimeter brickwork, ground floor

  • Internal blockwork to ground floor

  • Internal walls, 1st floor

  • External boarding, windows & balcony doors 1st – 3rd floor

  • Roof truss installation & waterproofing

Block C

  • Brickwork - ground -1st floor

  • High level mechanical & electrical services, lower ground floor

  • Ground floor – internal walls

  • 1st floor – ductwork installation & internal walls

  • 2nd floor – floor screeding

  • 3rd floor – internal walls

  • Pitch roof covering & waterproofing

Otto Close

  • External brickwork, plots 8-11

  • Second lift of scaffolding, plots 5-7

  • Floor joist installation, plots 1-4 due to complete next week

Saturday 9 November (08.00 – 13.00)

  • Continuation of works listed above

 

Noisy works

  • Plant movement (excavators and dumpers)

Deliveries

  • Muck removal lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

Note/Future works

  • Safety notice: Please ensure that all traffic signs and barriers aimed at passing pedestrians are observed at all times. Marshalls are on site monitoring all construction traffic, and we request that you follow their instructions, particularly if you are with children, for your and their own safety.

  • Naming ballot - thank you for those who have already voted! Please remember to vote on your choice of name for the new building. Link to ballot here

  • Halloween sweets – Hannah distributed some sweets for Halloween from Lovell this week. If you were away and your children would like some, we have some pots left over. Please contact us if you’d like us to drop them to you!

If you have any queries, please contact us on info@sydenhamhillproject.com

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

For site emergencies, please contact:

Andrew Neary             07436 049 480

Hannah Morgan          07769 306 933

Hamid Vafaeifard 07587 103 467

Dion King                     07901 737 269

Laury Jancauskas 07502 600 834

Best Wishes,

The Sydenham Hill Project Team