Sydenham Hill Estate Weekly Works Update: w/c Monday 21 October 2024

Dear Neighbour,

 

Please find below the activities that are scheduled to take place from the week commencing Monday 21 October 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 21 - Friday 25 October

Block A

  • Brickwork to 2nd floor & main entrance atrium and columns between blocks A & B

  • Internal walls

  • High level service installation to corridors

  • Mechanical & electrical installation - 1st & 2nd floor

  • Testing of mechanical pipework

  • External boarding & windows – 3rd floor

  • Roof waterproofing works to gutter

  • Pitched roof tiling

Block B

  • Scaffolding installation to perimeter

  • Perimeter brickwork, ground floor

  • Internal blockwork to ground floor

  • External boarding & windows, 1st & 2nd floor

  • Electrical installation to generator room

  • Installation of remaining stacks through the building

  • Roof truss installation

  • Thames Water connection by gate 1 on Sydenham Hill = see note.

Block C

  • Brickwork to lower ground floor

  • High level mechanical & electrical services, lower ground floor

  • Floor screed, 1st floor

  • Internal walls 2nd floor

  • Window installation, 3rd floor

  • Pitch roof covering & waterproofing

Otto Close

  • External brickworks, plots 8-11

  • Scaffolding,plots 1-7

  • Floor joist installation, plots 1-4

Saturday 26 October (08.00 – 13.00)

  • Continuation of works listed above

 

Noisy works

  • Plant movement (excavators and dumpers)

Deliveries

  • Muck removal lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

Note/Future works

  • Safety notice: Please ensure that all traffic signs and barriers aimed at passing pedestrians are observed at all times. Marshalls are on site monitoring all construction traffic, and we request that you follow their instructions, particularly if you are with children, for your and their own safety.

  • Thames Water works: Thames Water have started their connection of the water mains on Monday 14 October as planned.  They have a footpath and road closure in place outside Gate 1, and works are planned to complete Thursday 24 October.

  • Pathway hoarding lighting: We have ordered new lights and mirrors for the hoarding by Otto Close and Rose Court which will be fitted this week.

  • Recycling/Rubbish collection, Otto Close: We have been informed that recycling bin collections have been missed which could be due to construction lorries blocking the road.  Please note that the Lovell traffic marshalls will bring down the bins should the collection not take place before 8am and can also help with emptying the bins if required.   

  • Change of Date – Meet the Contractor.   We had previously asked you to ‘save the date’ for a meet the contractor event on 23 October.  This will now take place later in November – we will send details once the date is confirmed.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

For site emergencies, please contact:

Andrew Neary             07436 049 480

Hannah Morgan          07769 306 933

Hamid Vafaeifard 07587 103 467

Dion King                     07901 737 269

Best Wishes,

The Sydenham Hill Project Team