Sydenham Hill Estate Weekly Works Update: w/c Monday 14 October 2024

Dear Neighbour,

 

Please find below the activities that are scheduled to take place from the week commencing Monday 14 October 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 14 - Friday 18 October

Block A

  • Brickwork to 2nd floor & main entrance atrium between blocks A & B

  • Internal walls

  • Floor screeding, 3rd floor & staircase

  • Mechanical & electrical installation - 1st & 2nd floor

  • Roof waterproofing works to gutter

  • Pitched roof covering works

Block B

  • Final clearance of materials by framework contractor

  • Hoist installation to transport materials between floors

  • Scaffolding installation to perimeter

  • Brickwork, ground floor

  • External boarding & windows installation, 1st floor

  • Floor screeding & internal walls, ground floor

  • Mechanical & electrical installation to generator room

  • Installation of remaining stacks through the building

  • The new Thames Water connection is planned to commence on Monday 14 October. They will be digging outside gate 1 on Sydenham Hill.

Block C

  • Internal walls, lower ground floor and high level mechanical & electrical services

  • Electrical installation to riser ground floor to 3rd floor

  • Internal walls, 1st floor

  • Window installation, 3rd floor

  • Roof truss installation & waterproofing

Otto Close

  • External brickworks, plots 8-11

  • Scaffolding,plots 1-7

  • Floor joist installation, plots 1-4

Saturday 19 October (08.00 – 13.00)

  • Continuation of works listed above

 

Noisy works

  • Plant movement (excavators and dumpers)

Deliveries

  • Muck removal lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

Note/Future works

  • Safety notice: Please ensure that all traffic signs and barriers aimed at passing pedestrians are observed at all times. Marshalls are on site monitoring all construction traffic, and we request that you follow their instructions, particularly if you are with children, for your and their own safety.

  • Thames Water works: The new connection from Thames Water is planned to commence 14 October and is planned to complete withing nine days. Thames Water will be digging outside gate 1 to form the connection. When we have further information regarding these works and any road closures, we will share this with you.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

For site emergencies, please contact:

Andrew Neary             07436 049 480

Hannah Morgan          07769 306 933

Hamid Vafaeifard 07587 103 467

Best Wishes,

The Sydenham Hill Project Team