Sydenham Hill Estate Weekly Works Update: w/c Tuesday 27 August 2024

Dear Neighbour,

 

Please find below the activities that are scheduled to take place from the week commencing Tuesday 27 August 2024 in connection with the Sydenham Hill Estate Redevelopment Project. Please note, no works will be occurring on Monday 26 August, due to the bank holiday.

Tuesday 27 - Friday 30 August

Block A

  • External sheathing boarding in progress

  • Window installation on 1st and 2nd floors ongoing

  • Scaffolding and monoflex ongoing

  • Internal mechanical fittings in progress

  • External façade ongoing

  • Blockwork to internal walls ongoing

  • Roof truss installation ongoing

  • Waterproofing ongoing

Block B

  • Building structure for concrete on the 6th floor ongoing

  • Metsec on ground and 1st floors in progress

  • Substation installation

  • Internal mechanical fittings in progress

  • Building structure for the 5th Floor ongoing

  • Service trenches for water mains installation in sections. Meter installation connection from Thames Water due imminently; road closure for Thames Water works rescheduled to October* 

  • Scaffolding from ground floor to 3rd floor ongoing

*Please note that the date subject to change, depending on availability

Block C

  • Roof overruns, upstands, and waterproofing ongoing

  • Stair core installation in progress

  • External sheathing boarding in progress

  • Internal mechanical fittings in progress

  • Scaffolding from 1st to 4th floors ongoing

  • Metsec on 1st and 2nd floors ongoing

  • External façade ongoing

Otto Close

  • Service trench excavation, located at junction with Kirkdale – set to be finished early September.

  • Electrical cable installation

  • Backfilling service trench

  • Mains water trench excavation

  • Laying mains water pipe

  • Rainwater pipe drainage connection works to front of the houses

  • Scaffold matt works

  • Clearing materials off site

  • Substructure brickwork works

  • Waterproofing to substructure brickwork

  • Internal blockwork ongoing

 

Saturday 31 August (08.00 – 13.00)

  • Continuation of works listed above

 

Noisy works

  • Plant movement (excavators and dumpers)

Deliveries

  • Muck removal lorries in and out of main gate

  • Concrete lorries in and out of the delivery gate

  • Transformer being delivered for substation installation

 

Note/Future works

  • We have upgraded our security system to monitor night-time activity on-site, which now includes an alarm and an automated voice alert in the event of any intruders. While we hope such incidents do not occur, it is essential that these measures are implemented to ensure public safety

  • Any extensions to site working hours will continue to be communicated in advance through Planning and CommComm, respectively.

  • Regarding Otto Close works, please be advised that a partial road closure will be in place for the duration of service enabling works.Access to Otto Close will be maintained at all times

If you have any queries, please contact us on info@sydenhamhillproject.com

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

For site emergencies, please contact:

Andrew Neary             07881 023 254

David Olatunji             07340 379 305

Hannah Morgan          07769 306 933

Laurynas Jancauskas  075025 600 834

Best Wishes,

The Sydenham Hill Project Team