Dear Neighbour,
Please find below the activities that are scheduled to take place from the week commencing Tuesday 2 April 2024 in connection with the Sydenham Hill Estate Redevelopment Project.
Tuesday 2 - Friday 5 April
Block A:
Building the structure to hold the concrete being poured for the first floor
Vertical Concrete columns consisting of steel work and concrete to hold up the concrete to the first-floor slab during construction
Insulation and waterproofing
Drainage Installation
Block B:
Cutting down concrete to foundation piles
Lift shaft
Steelwork to concrete floor
Drainage Installation
Block C:
Building the structure to hold the concrete being poured for the first floor
Vertical steel work for ground concrete floor
Concrete retaining wall
Otto Close:
Drainage diversion works by 23 Lammas Green
Kingpost install to hold back the ground level.
Saturday 6 April
Works will take place at Blocks A-C at Mais House between our permitted hours of 8am – 1pm. The works carried out include drainage installation, steel fixing, formwork and material reorganisation.
Noisy works
• Plant movement (excavators and dumpers)
Deliveries
• Muck removal lorries in and out of main gate
• Concrete lorries in and out of the delivery gate
Note
Please note that we anticipate that works will be taking place on Saturdays from April onwards between the permitted hours of 8am – 1pm as we need to make up lost time due to the weather over the winter. We will notify you every week of any Saturday works.
If you have any queries, please contact us on info@sydenhamhillproject.com
Best wishes,
The Sydenham Hill Project Team
General Site Working Hours:
Monday to Friday 08:00 to 18:00
Saturday 08:00 to 13:00
For site emergencies, please contact Lovell on 020 8731 3800 (0800 030 4690 out of hours)