Please find below the activities that are scheduled to take place from the week commencing Monday 3 March 2025 in connection with the Sydenham Hill Estate Redevelopment Project.

Monday 3 - Friday 7 March; Saturday 8 March (08.00 - 13.00)

 Block A

  • Brickwork snagging

  • Scaffold Strike & window cleaning down to 2nd floor

  • Staircase painting & conduit install

  • Removal of scaffold to lift shaft

  • Plastering & boarding of corridors & ceilings

  • Decoration of ground, 1st & 2nd floor apartments

  • Appliance delivery & installation, 2nd floor

  • Tiling - 3rd floor bathrooms & kitchens

  • Fire curtain installation, 3rd floor apartments

  • Vaulted ceiling boarding to 3rd floor

  • Electrical installation in atrium

Block B

  • Brickwork, 3rd floor perimeter & 5th floor

  • Painting liftshafts

  • Plaster to staircore

  • Mechanical & electrical first fix, ground floor apartments

  • High level mechanical services installation, 4th & 5th floor

  • Internal walls, 6th floor

  • Roof truss installation to 4th floor roof

Block C

  • Plant connections in plantroom

  • Brickwork, 3rd floor

  • Removal of scaffold to lift shaft

  • Ceiling & corridor wall closures & plastering

  • Snagging & inspection of high-level services, 3rd floor

  • Tiling to roofs

Otto Close

  • Blockwork to 2nd floor, houses 1-2

  • Scaffold ‘birdcage’, houses 3-4

  • Roof covering, houses 5-7

  • Brick & blockwork for 2nd floor, houses 8-11

  • No large deliveries to Otto Close expected this week

Future works/deliveries

  • The smaller crane is now due to be removed on Saturday 15 March. We will notify you in next week’s update of further details, as it may be that this may run past 1pm.

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best Wishes,

The Sydenham Hill Project Team

 

General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 

 For site emergencies, please contact:

Andrew Neary 07436 049 480

Hannah Morgan          07769 306 933

Hamid Vafaeifard        07587 103 467

Dion King                     07901 737 269

Laury Jancauskas         07502 600 834

Security 07759 833 036