Sydenham Hill Estate Weekly Works - w/c 29 April 2024

Dear Neighbour,


Sydenham Hill Estate Weekly Works Update:  w/c Monday 29 April 2024

 

Please find below the activities that are scheduled to take place from the week commencing Monday 29 April 2024 in connection with the Sydenham Hill Estate Redevelopment Project.

 

*Notification for Saturday 27 April:

We have received notice that the concrete delivery will be delayed tomorrow, therefore works may overrun the 1pm finish time to enable the concrete pour to block C.  All works will cease at 1.15pm and vehicles out by 1.30pm at the latest.


Monday 29 April – Friday 3 May

 Block A:          

  • Building the structure to hold the second floor.

  • Perimeter drainage installation

Block B:         

  • Cutting down concrete to foundation piles.

  • Steelwork to concrete floor

  • Drainage installation and waterproofing                    

Block C:          

  • Building the structure to hold the concrete for retaining wall

  • Steel work for the structure

     

Otto Close:     

  • Boundary hoarding line works - by steps from alleyway to Lammas Green - *See note/diagram below

  • Reduce level dig to attenuation tank

     

Saturday 4 May

Blocks A/B/C: 

  • Concrete pour

  • Material re-organisation

  • Drainage & decking installation

  • Steel fixing

Otto Close:     

  • No planned works

Noisy works

• Plant movement (excavators and dumpers)





Deliveries

• Muck removal lorries in and out of main gate

• Concrete lorries in and out of the delivery gate





Note

  • Further to previous notifications relating to works to the manholes/sewer connections in Otto Close, these are on hold due to re-sequencing and are likely to recommence in w/c 6 May 2024.

  • We are aware of the damage to the railings in Otto Close and will be carrying out the necessary repairs in the coming weeks.

  • In order to proceed with planned works to the footpath, we will need to change the hoarding line which will mean diverting pedestrian access around the lower steps of the alleyway to the zig-zag route. 

    Please see diagram in red below – the red area will be fenced off, and access will be via the blue arrows. This diversion will be in place until Friday 10 May.


     

Plan showing diversion route during hoarding line works

If you have any queries, please contact us on info@sydenhamhillproject.com

 

Best wishes,

The Sydenham Hill Project Team

 

 General Site Working Hours:

Monday to Friday 08:00 to 18:00

Saturday 08:00 to 13:00

 